With only 12 weeks before the Rugby world cup 2011 kicked off Stewart Construction were called in to carry out the landscaping package what had to be completed for the world cup. The project involved 2500m2 of exposed aggregate concrete, 150no precast seats and precast feature walls. Due to the tight timeframe it required careful co-ordination of sub-contractors for a successful completion. At its peak Stewart Construction had 12 personnel working on the site with 12 hour days, 6 days a week